    Hi All,

    I needed a function similar to Excels WORKDAY to provide a Date in advance excluding Weekends (and Holidays [Optional]).

    I tried a few methods, and ended up with this.

    Simply build a list of Dates and iterate them removing Weekends and Holidays, then pick the number of days ahead. It is useful for forecasting graduation dates for a given course of length n. (Note, it is Aus centric)

    Please comment

    Code:
    Option Explicit On
    Option Strict On
    
        Public Function FindDate(ByVal startdate As Date, ByVal days As Integer, Optional ByVal holidays As List(Of Date) = Nothing) As Date
            ' *****************************************************
            ' Validate
            If days < 1 Then Err.Raise(vbObjectError + 513, "Module.ForcastDate.Limit", "Minimum number of 'days' exceeded. The allowed lower limit is 1.")
            If days > 2000 Then Err.Raise(vbObjectError + 2000, "Module.ForcastDate.Limit", "Maximum number of 'days' exceeded. The allowed maximum limit is 2000.")
            ' *****************************************************
    
            Dim dates As New List(Of Date)
    
            ' We need to ensure that enough Dates exist AFTER the Weekends and Holidays are removed so the 'days' ahead will hit a Date and not error out on 'Index out Of Range'
            ' Therefore, pad the offset out using the (arbitrary) functions below
            Dim offset As Integer
            If days < 6 Then
                offset = days + Convert.ToInt16(days * 2)
            Else
                offset = days + Convert.ToInt16(days * 0.5)
            End If
            If Not IsNothing(holidays) Then offset += Convert.ToInt16(holidays.Count * 2)
    
            Try
                For intCount = 0 To offset - 1 ' Include the startdate as the point to calculate from by indexing as "0 to n" days - 1
                    dates.Add(DateAdd(DateInterval.Day, intCount, startdate).Date)
                Next
                ' Use LINQ to remove Weekends
                For Each _date In dates.Where(Function(i) i.Date.DayOfWeek = DayOfWeek.Saturday Or i.Date.DayOfWeek = DayOfWeek.Sunday).ToArray()
                    dates.Remove(_date)
                Next
                ' Now, remove all Holidays
                If Not IsNothing(holidays) Then
                    For Each _holiday In holidays
                        dates.Remove(_holiday.Date)
                    Next
                End If
    
                Return dates.Item(days - 1)
    
            Catch ex As Exception
                ' Return an arbitary Date
                Return #1/1/1900#
            End Try
    
        End Function
    Use:
    Code:
            Dim workday As New clsWorkday
    
            Dim holidaylist As New List(Of Date)
            holidaylist.Add(Convert.ToDateTime("11/7/2012"))
            holidaylist.Add(Convert.ToDateTime("12/7/2012"))
            Try
                MessageBox.Show(FindDate(Convert.ToDateTime("09/7/2012").Date, 4, holidaylist).ToShortDateString)
               MessageBox.Show(FindDate(Convert.ToDateTime("09/7/2012").Date, 160).ToShortDateString)
            Catch ex As Exception
                MsgBox(ex.Message)
                MsgBox(ex.Source)
            End Try
    Last edited by Bruce Fox; Jul 10th, 2012 at 04:59 PM.

  2. #2
    I'm about to be a PowerPoster! kleinma's Avatar
    Join Date
    Nov 2001
    Location
    NJ - USA (Near NYC)
    Posts
    23,373

    Re: Workday

    Same results with this refactored one. It could probably be tweaked even further.

    Code:
        Public Function FindDate2(startdate As Date, days As Integer, Optional holidays As List(Of Date) = Nothing) As Date
    
            'VALIDATION
            If days < 1 Then Throw New ArgumentException("Minimum number of 'days' exceeded. The allowed lower limit is 1.")
            If days > 2000 Then Throw New ArgumentException("Maximum number of 'days' exceeded. The allowed maximum limit is 2000.")
    
            Dim dateIncrement As Date = startdate 'USED TO INCREMENT THE DATE FORWARD
    
            Do Until days = 0 'LOOP UNTIL WE HAVE USED ALL THE NEEDED DAYS
                dateIncrement = dateIncrement.AddDays(1) 'GET THE NEXT DAY SO IT CAN BE TESTED TO BE A WEEKEND OR HOLIDAY
                If dateIncrement.DayOfWeek = DayOfWeek.Saturday OrElse
                    dateIncrement.DayOfWeek = DayOfWeek.Sunday OrElse (holidays IsNot Nothing AndAlso holidays.Contains(dateIncrement)) Then
                    Continue Do 'WEEKEND OR PASSED IN HOLIDAY, GO ON TO NEXT DAY
                Else
                    days -= 1 'A WEEKDAY WAS FOUND, DECREMENT DAYS COUNTER BY 1
                End If
            Loop
    
            Return dateIncrement.AddDays(-1) 'RETURN THE FINAL DATE WE GOT TO (-1)
    
        End Function

  3. #3

    Thread Starter
    INXSIVE Bruce Fox's Avatar
    Join Date
    Sep 2001
    Location
    Melbourne, Australia
    Posts
    7,429

    Re: Workday

    Hi kleinma,

    Thanks for the feedback and tweaks

    Unfortunately, 'FindDate2' exhibits the same issue of not aggregating days, weekend & holidays to provide the calculated offset to jump forward.

    I had the same problem (except I was using recursion) to pass back the intermediate Date in case it fell on a Weekend/Holiday.

    To demonstrate, take this example:
    Start Date is: Monday 09 July 2012, number of days to complete the Course is 10.


    09/July/2012, 10 days ahead is Friday the 20th July 2012. ('FindDate2' yields 22nd July 2012)

    At least you provided something better to work with, I think I have a fix (using FindDate2) and I will post back later today.

  4. #4

    Thread Starter
    INXSIVE Bruce Fox's Avatar
    Join Date
    Sep 2001
    Location
    Melbourne, Australia
    Posts
    7,429

    Re: Workday

    Matt,

    I'll apologise now, as I think I wasn't clear, and confussed the issue using the word 'exclude'!

    What I should have stated, was that a StartDate is provided, and the length of Course in days (n) is provided.

    The Function, needs to return the Date that is n days ahead 'discounting/passing by' Weekends (and Holidays).

    In other words, Weekend and Holidays cannot be absorbed as a Course day, just working days.


    My bad
    Last edited by Bruce Fox; Jul 10th, 2012 at 08:30 PM.

  5. #5

    Thread Starter
    INXSIVE Bruce Fox's Avatar
    Join Date
    Sep 2001
    Location
    Melbourne, Australia
    Posts
    7,429

    Re: Workday

    For now, I have reverted back to the table approach. It is still slightly wasteful due to the padding, but I have tried small lengths, and large ones successfully (for example in a year, approx 1/3 of the days are weekends):
    Code:
        Public Function GraduationDate(ByVal startdate As Date, ByVal courselength As Integer, Optional ByVal holidays As List(Of Date) = Nothing) As Date
            ' *****************************************************
            ' Validate
            If startdate.DayOfWeek = DayOfWeek.Saturday OrElse startdate.DayOfWeek = DayOfWeek.Sunday OrElse
                (holidays IsNot Nothing AndAlso holidays.Contains(startdate)) Then Throw New ArgumentException("The Start Date must be a Weekday.")
            If courselength < 1 Then Throw New ArgumentException("Minimum Course Length exceeded. The allowed lower limit is 1.")
            If courselength > 2000 Then Throw New ArgumentException("Maximum Course Length exceeded. The allowed upper limit is 2000.")
            ' *****************************************************
            Dim dates As New List(Of Date)
    
            ' We need to ensure that enough Dates exist AFTER the Weekends and Holidays are removed so the 'courselength' ahead will hit a Date
            Dim offset As Integer = (courselength + holidays.Count) * 2
    
            dates.Add(DateAdd(DateInterval.Day, 1, startdate).Date)  ' Include the Start Date
    
            For intCount = 1 To offset
                startdate = startdate.AddDays(1)
                If startdate.DayOfWeek <> DayOfWeek.Saturday AndAlso
                    startdate.DayOfWeek <> DayOfWeek.Sunday AndAlso
                    Not (holidays IsNot Nothing AndAlso holidays.Contains(startdate)) Then
                    dates.Add(startdate.Date)
                End If
            Next
    
            Return dates.Item(courselength - 1)
    
        End Function
    Calling
    Code:
            Dim holidaylist As New List(Of Date)
            holidaylist.Add(Convert.ToDateTime("10/7/2012"))
            holidaylist.Add(Convert.ToDateTime("11/7/2012"))
            holidaylist.Add(Convert.ToDateTime("13/7/2012"))
            Try
                MessageBox.Show(GraduationDate(Convert.ToDateTime("09/7/2012").Date, 3, holidaylist).ToShortDateString)
            Catch ex As Exception
                MsgBox(ex.Message)
            End Try
    (Note: If using Excel to validate, the course length needs to be n-1 as Excel does not include the start date)