Hi Folks,
We have an application with 178 forms.
The client decided to replace all third-party controls with microsoft controls.
So we decided to go with basic controls like command buttons / check boxes / option buttons / frames / date controls etc.
This took about 6 working hours for 1 form. Now this was a fairly large form. So I averaged out to 3 working hours per form for estimation purpose.
Now I estimated that the change will take 178 * 3 = 534 working hours. That translates to roughly 66 person days. I informed the client about it. He says its crazy and tells me that it should be done in 20 days. Though our negotiation has not yet finished, how do I convince him to accept my estimate?
My developers are the ones who are terribly upset and are talking of quitting all the time.
Everything that has a computer in will fail. Everything in your life, from a watch to a car to, you know, a radio, to an iPhone, it will fail if it has a computer in it. They should kill the people who made those things.- 'Woz'
save a blobFileStreamDataTable To Text Filemy blog
Posting Permissions
- You may not post new threads
- You may not post replies
- You may not post attachments
- You may not edit your posts
-
Forum Rules
|
Click Here to Expand Forum to Full Width
|